Timescale
The table below shows the draft time scale for the project. Please note some of the information is still subject to change or approval.
| Objective | Start Date | Finish Date | Fundrising Key Targets |
|---|---|---|---|
| Outline Business Case (OBC) approved & Initial Concept Design | Nov 2007 | ||
| Commence Full Business Case & Full Planning Design | Nov 2007 | ||
| OJEU tender for full design | Nov 2007 | March 2008 | |
| Appoint full design team for project | May2008 | ||
| Complete planning application documention & apply for planning approval | Sept 2008 |
Nov 2008 | |
| Planning approval period | Dec 2008 | Feb 2009 | |
| Complete Full Business Case | March 2009 | £2.7m | |
| Full Business Case approval | March 2009 | ||
| Design and Tender Stages | April 2009 | Dec 2009 | |
| Design & Build Contract awarded | Dec 2009 | £4.0m | |
| Enabling works - Reprovision of existing facilities (design, tender & construction stages) | April 2009 | July 2009 | |
| *Oxygen plant & waste store | July 2009 | ||
| *Changing area (separate project) | July 2009 | ||
| *Cycle Shead (separate project) | July 2009 | ||
| NICU Construction (New build) | Dec 2009 | Jan 2011 | |
| Construction Complete | Jan 2011 | ||
| Commissioning | Jan 2011 | End Jan 2011 | |
| Department Operational | Feb 2011 | £4.7m |